12-04-2009: ABB has won orders worth $73 million from Kernkraftwerk Leibstadt (KKL) to refurbish and upgrade the non safety related operational control and automation system at their 1,220 megawatt Leibstadt nuclear power plant in Switzerland.

For this upgrade, ABB will replace the existing multiple control systems with a single solution, based on its Extended Automation System 800xA. ABB will design, engineer, install, commission and test the installation, and is also responsible for upgrading the KKL simulator used for operator training.

To avoid any disruption in electricity supplies, the project will be carried out in phases that coincide with planned annual outages, starting in 2011 and running until 2018. Prior to installation, each stage of implementation will be extensively tested on a full-size test bed and on the KKL training simulator.

The initial scope of the new control system will include the ventilation systems, the demineralization plant and the cooling tower make-up water system, which makes up for losses due to evaporation. It will later be extended to incorporate the water steam cycle, the turbine controls, operational reactor support systems and other elements, under a frame agreement between ABB and KKL.

Watchlist

This is where you can add this news to your personal favourites

Facts, background information, dossiers
Most read news
Your browser is not current. Microsoft Internet Explorer 6.0 does not support some functions on Chemie.DE